EMPLOYER
Department of Roads and Transport

CONSULTANT
Stewart Scott International in JV with Saunders & Wium Consulting Engineers

YEAR COMPLETED
2007

VALUE AT COMPLETION
R218M

LOCATION
South Africa, Eastern Cape

PROJECT TYPE
Road Construction and Rehabilitation

DESCRIPTION
The construction of a Provincial Road, 33km long, including bulk earthworks, layerworks, bituminous surfacing, associated stormwater and sub-surface drainage, road signage, road markings, safety features, fencing and stock control gates, underpasses, the opening and subsequent rehabilitation of borrow pits, plus the landscaping and finishing of the roadway. There are 5 Bridge structures and a number of large box culverts included in the project. Bulk earthworks-955 500m3 fill, 390 000m3 spoil Layerworks-SSG-138 850m3, subbase-90 700m3, G1 basecourse-61 500m3 Surface and primes-314 000 litres prime, Asphalt-356 000m2 Subsoil drains-30 000m Open drains-61 000m3 Gabions-5 350m3 Landscaping-500 000m2 Concrete side drains-21 700m Stormwater culverts- 4 300m Bridges- 5 No Insitu underpass structures- 4 No