CLIENT
Growthpoint Properties and Illovo Sugar
PROJECT ARCHITECT
EPA
CONTRACT VALUE
ZAR 232 Million
LOCATION
Sandton, Johannesburg
PROJECT TYPE
Building Commercial
DESCRIPTION
Four level super basement parking area (21 000 m2) and two independent 5 storey towers for Growthpoint Properties and Illovo Sugar Offices.
CONTRACT PERIOD
16 Months
CLIENT
Dipalopalo Concession (Pty) Ltd
ARCHITECT/ENGINEER
GLH Architects / Terra Ether JV
VALUE AT COMPLETION
ZAR 1.4 Billion
LOCATION
Pretoria, South Africa
PROJECT TYPE
Building Commercial
DESCRIPTION
New Head Office in Pretoria for the
Department of Statistics South Africa
CONTRACT PERIOD
April 2014 – June 2016
CLIENT
SANRAL
ARCHITECT/ENGINEER
SMEC
VALUE AT COMPLETION
ZAR 143 Million
LOCATION
N1 Botlokwa Section 28 km 43,8 and km 45,7
PROJECT TYPE
Roads & Bridges
DESCRIPTION
The upgrading of the Matoks intersection on the N1 by constructing two new pedestrian bridge and the one main vehicle bridge , 1,9km service road B and upgrading of the N1 for 1,5 km.
CONTRACT PERIOD
July 2014 – May 2016
CLIENT
Johannesburg Development Agency
ARCHITECT/ENGINEER
Hatch/GOBA
VALUE AT COMPLETION
ZAR 85 Million
LOCATION
Sandton, Katherine Street
PROJECT TYPE
Roads & Bridges
DESCRIPTION
The Section 8 of the Rea Vaya BRT in Johannesburg, will service the proposed route between the Gautrain Station in the Sandton CBD and an inter-modal facility adjacent to Pretoria Main Road serving the Alexandra community.
CONTRACT PERIOD
May 2014 – June2015
CLIENT
eThekwini Transport Authority
ARCHITECT/ENGINEER
MCA Joint Venture
VALUE AT COMPLETION
R 293 mil (In JV with Thekwane, Oteo, Phakama, Ngosi Trading and Lakeshore)
LOCATION
Pinetown, KZN
PROJECT TYPE
Roads & Bridges
DESCRIPTION
Section 1 runs along Josiah Gumede road (old Main road), from Anderson road to Beviss road and consists of the dedicated ROW lanes for the new Integrated Rapid Public Transport Network, a total length of Section 1 is 1550m and is the main carriageway through Pinetown CBD.
Section 2 runs along Anderson road from Josiah Gumede road to Davidson road south and is 400m in total.
CONTRACT PERIOD
May 2014 – December 2015
CLIENT
Growthpoint Properties Ltd
ARCHITECT/ENGINEER
Elphick Proome Architects
VALUE AT COMPLETION
ZAR 81 Million
LOCATION
Umhlanga Ridge – KZN
PROJECT TYPE
Building
DESCRIPTION
Construction of the new Boulevard Office Development comprising approximately 5500m2 of Offices and 10,000m2 of structured parking and related external works
CONTRACT PERIOD
March 2015 – April 2016
CLIENT
eThekwini Transport Authority
ARCHITECT/ENGINEER
HHO
VALUE AT COMPLETION
ZAR 349 Million (In joint venture with Thekwane, Phakama, Ethos and Lakeshore)
LOCATION
Inanda, KZN
PROJECT TYPE
Building
DESCRIPTION
The portion of the ROW covered under this contract is approximate 3.6km long and extends from Bridge City to the proposed IRPTN Bus Depot, and continues from Malandela intersection MR577
CONTRACT PERIOD
April 2014 – January 2016
CLIENT
V&A WATERFRONT HOLDINGS (PTY) LTD
ARCHITECT/ENGINEER
MLC QUANTITY SURVEYORS
VALUE AT COMPLETION
ZAR 500 Million
LOCATION
V&A WATERFRONT, CAPE TOWN
PROJECT TYPE
Building
DESCRIPTION
The construction of 35000m2 of new office, gym &
residential space within the Clock Tower precinct of the V&A
Waterfront
CONTRACT PERIOD
March 2015 – September 2016
CLIENT
The Oasis Joint Venture
ARCHITECT/ENGINEER
Raymond Alexander Architects
VALUE AT COMPLETION
R120 Million
LOCATION
Cape Town
PROJECT TYPE
Civils
DESCRIPTION
The work embodied in the contract comprises, the construction of 47 luxury apartments over 11 floors above two levels of undercover parking, 3 garden apartments, a sales/admin building of approximately 170m2 and landscaped gardens.
CONTRACT PERIOD
16 February 2015 – 6 June 2016
CLIENT
Abland (Pty) Ltd
ARCHITECT/ENGINEER
GLH Architects
VALUE AT COMPLETION
R465 Million
LOCATION
Rosebank
PROJECT TYPE
Building
DESCRIPTION
Construction of new office block for Abland Property Group.
Office block consists of 7 parking levels (1 underground) and 6 above ground.
7 levels of offices are for Redefine and Virgin Active.
Facades are 70 % glass and vertical transport consists of 2 main lift cores of 3 lifts each and 1 glass scenic lift.
COMMENCEMENT
14 July 2014
ESTIMATED COMPLETION
22 October 2015