Polokwane Bypass
EMPLOYER
SANRAL
CONSULTANT
KBK Engineers
YEAR COMPLETED
2011
VALUE AT COMPLETION
R359M
LOCATION
South Africa, Limpopo
PROJECT TYPE
Road Construction and Rehabilitation
Mall of the North
EMPLOYER
Resilient, Flanagan and Gerard and the Moolman Group
CONSULTANT
MDS Architects
YEAR COMPLETED
2011
VALUE AT COMPLETION
R650m
LOCATION
South Africa, Limpopo, Polokwane
PROJECT TYPE
Retail
DESCRIPTION
Double level regional shopping centre
Foskor extension
EMPLOYER
Foskor (Pty) Ltd
CONSULTANT
Bateman Engineering
YEAR COMPLETED
2010
VALUE AT COMPLETION
R57M
LOCATION
South Africa, Limpopo, Phalaborwa
PROJECT TYPE
Mining
DESCRIPTION
Extension to debottlenecking plant
Pprust Isa Mills
EMPLOYER
Anglo Platinum
CONSULTANT
Vhumbanani Projects
YEAR COMPLETED
2009
VALUE AT COMPLETION
R30M
LOCATION
South Africa, Limpopo
PROJECT TYPE
Heavy Industrial Plants
DESCRIPTION
Five new mills, MCC building and various small buildings
Peter Mokaba stadium
EMPLOYER
Polokwane Municipality
CONSULTANT
PRISM Architects
YEAR COMPLETED
2009
VALUE AT COMPLETION
ZAR 1bn / US $125m
LOCATION
South Africa, Limpopo, Polokwane
PROJECT TYPE
Leisure, Recreation, Education
DESCRIPTION
7 levels on west side; 60,000m3 concrete; 80,000m2 area; 46,000 seater; 4,400 tons rebar steel
PPRust Workshops
EMPLOYER
Rustenburg Platinum
CONSULTANT
Semane Consulting Engineers
YEAR COMPLETED
2008
VALUE AT COMPLETION
R129M
LOCATION
South Africa, Limpopo, Mokopane
PROJECT TYPE
Industrial Buildings
Elements Private Golf Reserve
EMPLOYER
Klaprops 69 (Pty) Ltd and The Clifford Family
CONSULTANT
Matkovich and Hayes
YEAR COMPLETED
2005
VALUE AT COMPLETION
R30M
LOCATION
South Africa, Limpopo
PROJECT TYPE
Golf Courses
DESCRIPTION
Elements Private Golf Reserve is set in a game reserve in the rolling foothills of the Waterberg. The full championship layout makes the most of the beautiful bushveld environment by incorporating and bringing into play many trees and pockets of indigenous bush. Trees line each hole and no fairways run next to each other making it a remarkable and challenging golf experience.
Chuniespoort
EMPLOYER
Northern Province Provincial Government
CONSULTANT
SNA
YEAR COMPLETED
1994
VALUE AT COMPLETION
R6.4M
LOCATION
South Africa, Limpopo, Pietersburg
PROJECT TYPE
Road Construction and Rehabilitation
DESCRIPTION
Construction Involved the following: Rehabilitation of existing road between Pietersburg and Lebowa Gomo by adding climbing lanes, improving failed areas of layerworks and the realigning of the road through Chuniespoort by widening the existing road by means of a viaduct.5 km Climbing lanes, Intersections, 13 km Crack Sealing and Re-sealing,Construction of a bridge of 1 200 m consisting of both precast and insitu elements.