‹ › CLIENT Eskom VALUE AT COMPLETION R9.5bn LOCATION Ogies, South Africa PROJECT TYPE Civils DESCRIPTION Main civils work for the new 4800 MW Kusile coal power station COMMENCEMENT January…
NEWS
2015
‹ › CLIENT Abland (Pty) Ltd ARCHITECT/ENGINEER GLH Architects VALUE AT COMPLETION R465 Million LOCATION Rosebank PROJECT TYPE Building DESCRIPTION Construction of new office block for Abland Property Group. Office…
‹ › EMPLOYER Netcare Property Holdings (Pty) Ltd ARCHITECT/ENGINEER VDO Consulting VALUE AT COMPLETION R94 Million LOCATION Existing Milpark Hospital, Westcliff Ext 3. PROJECT TYPE Residential DESCRIPTION Demolition of existing…
‹ › EMPLOYER Akani Egoli ARCHITECT/ENGINEER Northpoint Architects VALUE AT COMPLETION R204 Million LOCATION Johannesburg, South Africa PROJECT TYPE Building DESCRIPTION Expansion of existing Casino Complex: Gaming Area , Gaming…
‹ › CLIENT Abland (Pty) Ltd ARCHITECT/ENGINEER Paragon Architects VALUE AT COMPLETION R880 Million LOCATION Sandton PROJECT TYPE Buildiing DESCRIPTION Demolitions, Earthworks and the construction of 7 basement parking levels…
‹ › CLIENT Discovery Joint Venture (Growthpoint / Zenprop) ARCHITECT/ENGINEER Boogertman & Partners VALUE AT COMPLETION R1.8 Billion LOCATION Sandton PROJECT TYPE Building DESCRIPTION Joint Venture with Tiber: Construction of…
WILSON BAYLY HOLMES – OVCON LIMITED Building and civil engineering contractors (Registration no. 1982/011014/06) ISIN No: ZAE 000009932 Share code: WBO (“WBHO” or “the Company”) TRADING STATEMENT The directors of…
2014
‹ › After the successful completion of Lubambe Mine’s Concentrator Civil works in Chililabombwe, Zambia, WBHO Zambia was in November 2012 awarded the civil works of the acid plant and…
‹ › The Ndola Expansion Project, in Zambia is funded by SAB Miller as part of their investment strategy into Africa. The project is being constructed in two phases at…
‹ › The Newtown junction project is situated in the heart of Johannesburg, and can be seen from the M1 South highway. The project consists of a 4 level basement…
‹ › In acknowledgment of the critical importance of providing potable and adequate water supplies to the domestic and commercial consumers of the lowland areas in Lesotho, the government of…
‹ › The successful completion of the 157Ha Tailing Storage Facility, including the bulk and detailed earthworks, was achieved at the end of May 2013, after 25 months of construction…
‹ › The Middelburg Water Reclamation project is a multi-billion rand BECSA (BHP Billiton Energy Coal South Africa) initiative. The aim of this project is to implement a number of…
‹ › WBHO Projects Mozambique and our subsidiary Renniks Construction are in partnership to undertake the Rehabilitation of Engen’s Beira Terminal. The project consists of demolition of steel fuel tanks,…
‹ › The Vale Tailings Storage Facility in Tete, Mozambique was awarded to WBHO on 3 June 2013 and work commenced on 3 July 2013. The majority of the work…
‹ › WBHO has commenced a wide variety of upgrades and additions to the Silverstar Casino complex. The lake has been filled in and will accommodate the Silverstar Square with…
‹ › This project is situated next to the R547 starting at Shondoni mine and makes its way towards Sasol Secunda. It kicked off with site establishment on 2 April…