EMPLOYER
Anglo Coal
CONSULTANT
Anglo Project Services
YEAR COMPLETED
2009
VALUE AT COMPLETION
R 194 Million
LOCATION
South Africa, Mpumalanga
PROJECT TYPE
Mining
DESCRIPTION
Bulk earthworks for teraces, dams, access roads & rail line. Cut to Spoil - 500 000 m³, Cut to Fill - 500 000 m³. Construction of stacker and reclaimer rail beams. 8536 m³ of Concrete, 800 tons Reinforced steel & 31356 Cast - in Bolts Services including stormwater culverts (1 km), concrete lined drains (7.4 km), sub soils (4 km), HDPE water lines (14.3 km) and sleeves (815 m).