This Link is a dual road with a median to allow a future rapid transport lane or rapid transport system to be placed between the two lanes. This road is 3.4 km long and will link the Dube Tradeport’s Tradezone area at King Shaka International Airport with the Watson Highway, which links Tongaat with the N2.
The scope of work included the construction of a proposed MRO or aircraft maintenance area. All the MRO cut (about 380,000m3) was used to create fill platforms for future expansion of Dube Tradeport. The bulk earthworks for the road was more than 820 000m3
Contract Duration: May 2012 – Oct 2014
Contract Value: ZAR 187 Million
Engineers: Virtual Consulting Engineers
Client: Dube Tradeport
Location: Watson Highway, Kzn