The gross building area of the project is nearly 500 000m2, the equivalent of 65 rugby pitches. There are over 7 500 parking bays, all structured parking.
The site handover was on the 9th September 2013, with the opening planned for Easter in April 2016
Contract Duration: 28 Months
Contract Value: ZAR 2.2 Billion
Engineers: Aurecon
Client: Atterbury
Location: Allandale, Waterfall Precinct.
53 Andries Street
Wynberg
Johannesburg
South Africa
2090
Tel: +27 11 321 7200
Fax: +27 11 887 4364
Email: wbhoho@wbho.co.za