EMPLOYER
Millennium Challenge Account – Mozambique

CONSULTANT
Jeffeares & Green

YEAR COMPLETED
2013

VALUE AT COMPLETION
US$ 35,500,000.00

LOCATION
Mozambique, Nacala

PROJECT TYPE
Dams

DESCRIPTION
Nature of work involves the following: Establishment of camp and plant on site Accommodation of traffic on public roads Construction of the following: Road works & Bridges Earth Dam and Concrete Dam Walls Retaining Walls Spillway Structure Outlet Pump house Mechanical & Electrical Services Dealing with water, the existing dam will not be drained but levels are to be lowered accordingly throughout the contract Maintenance of the works.