Vale Tailings Storage Facility

By 14 March 2014October 18th, 2021No Comments

The Vale Tailings Storage Facility in Tete, Mozambique was awarded to WBHO on 3 June 2013 and work commenced on 3 July 2013. The majority of the work is bulk earthworks with over a million cubic metres of fill material required for the northern embankment dam wall. There are also slot drains of 2.8 km and a spillway consisting of more than 5000m³ of gabion stones.

Contract duration:
July 2013 – June 2014

Contract value:
USD 17.5 Million

Engineers: 
Golder Associates

Client:
Odebrecht

Contractor:
WBHO Projects-Mozambique Limitada

Location:

Tete, Mozambique